1.1 |
Subject Matter (suggestion on how to draft the tender title) |
|
The construction of new resource efficient roads whose design considers wider environmental impacts. or The maintenance works or major rehabilitation of existing roads in a resource efficient manner which considers wider environmental impacts. |
|
1.2 |
Technical Specification (to be included in the terms of reference / technical specifications) |
|
Environmental Integration and Restoration Plan This criterion shall apply when suitable land for planting is available, which may include planting in any soft- engineered drainage infrastructure such as retention basins, ponds or artificial wetlands)An Environmental Integration and Restoration Plan shall be provided as part of the road design that includes the following details: – A site map indicating the type, location and quantities/densities of all plant species (only non-invasive and native plant species shall be included); – A description of the procedure used to select plant species and a brief rationale as to why each species is suitable for the particular environmental conditions on the site; – Planting bed requirements: soil/compost/growing media used and their depths, initial fertiliser application, use of mulch, sowing of grass seeds; – Planned measures to avoid soil erosion both prior to and after the establishment of vegetation cover; – Expected maintenance requirements of the vegetated areas. Included any irrigation, grass cutting, pruning or replacement of plants.The plan should be compiled in accordance with best practice guidelines such as those outlined in the COST 341 report or other similar literature. |
|
Verification: |
The design team or the DB tenderer or the DBO tenderer shall provide a copy of the Environmental Integration and Restoration Plan to the contracting authority. |
|
|
Monitoring of noise emissions during construction and maintenance (When planning permission or local/national legislation requires, or when specifically requested by the contracting authority)The design team or the DB tenderer or the DBO tenderer shall provide details of how temporary noise barriers (or permanent if part of the final design) shall be erected to reduce noise levels in the defined receptor area to less than X dB(A) as averaged LdEN and Y dB(A) as averaged Lnight values as defined in Annex I of the Environmental Noise Directive (2002/49/EC). |
|
Verification: |
The design team or the DB tenderer or the DBO tenderer shall submit: – a plan of the works site and receptor area as defined by the Environmental Impact Assessment, legislation or contracting authority where relevant; – a timetable of works, highlighting when the loudest works are to take place; – specification of the noise barrier location and approximate properties coupled with basic acoustic calculations that demonstrate that noise mitigation in the receptor area will be feasible. |
|
|
Traffic Congestion Mitigation Plan
A Traffic Congestion Mitigation Plan to be implemented during construction and maintenance activities, shall be presented with the road design and include:
– A timeline with expected construction and/or maintenance activities for the road service life; – Alternative routes for diverted traffic during such activities, if necessary.
If the design team or the DB tenderer or the DBO tenderer includes congestion solutions during the use phase and any maintenance actions based on tidal flow lanes or hard shoulders to be used as lanes, they shall present an LCC analysis, including user cost externalities due to congestion.
For those roads where intelligent traffic systems (ITS) are implemented for traffic management, the road shall be equipped with the devices needed to support the ITS: cameras, traffic lights, information screens and variable road signs.
|
|
Verification: |
The design team or the DB tenderer or the DBO tenderer shall provide the detailed traffic congestion mitigation plan, the LCC analysis in accordance with ISO 15686-5 (if required) and the descriptions of the ITS devices (if required). |
|
|
Incorporation of recycled content
A minimum of 15% by weight of recycled content, re-used content and/or by-products, as per the Waste Regulations S.L.549.63, shall be incorporated for the sum of the main road elements in the table below:
(CA shall opt from either one of the following)
New construction or major extension |
Maintenance and rehabilitation |
• Sub-grade, including earthworks and ground works;
• Sub-base
• Base, binder and surface or concrete slabs.
|
• Base, binder and surface or concrete slabs. |
The recycled content as well as the re-used content shall be calculated on the basis of an average mass balance of re-used, recycled materials and/or by-products according to how they are produced and delivered to site: – For each ready mixed batch from which deliveries are dispatched to the construction site in accordance with standards on:
• Aggregates EN 13242, EN 13285; • Asphalt pavement EN 13043, EN13108-1, EN 13108-2, EN 13108-3, EN 13108-4, EN 13108-5, EN 13108-6, EN 13108-7, EN 13108-8; • Concrete pavement EN 206, EN 12620, EN13877; • Hydraulically bound granular mixtures EN 14227 part 1 to 5; • Stabilised soil EN 14227 part 10 to 15
– On an annual basis for factory made slabs and elements with claimed content levels in accordance with EN 12620 an EN 206, EN 13877 and national legislation.
|
|
Verification: |
The design team or the DB tenderer or the DBO tenderer shall indicate the recycled content, re-used content and/or by-products quantifying the proportional contribution of the recycled content and/or re-used content to the overall weight of the specified road elements, based on the information provided by the producer(s) of the construction material.
The design team or the DB tenderer or the DBO tenderer shall describe how the recycled content will be calculated and verified, including, as a minimum, batch documentation as the Type Test report, factory production control documentation and delivery documentation, and how the third-party verification will be arranged during the construction phase.
|